Data center siting snapshot: Loudoun County, Virginia
What public records show about building a data center in Loudoun County: local and state data center rules, mapped high-voltage lines and the utilities on record. Every line links its source.
Line miles are measured from the archived HIFLD Transmission Lines layer inside the Census county boundary. Mapped lines are not available capacity.
What the public record shows
The archived HIFLD map indicates approximately 141.4 miles of 230 kV-and-above transmission line within Loudoun County, comprising 36.6 miles at 500 kV or more and 104.8 miles at 230 kV [1]. An additional 15.7 miles of 115–161 kV line are mapped in the area [2]. Virginia Electric & Power and The Potomac Edison hold the most mapped 115 kV+ line miles [3]. Twelve named line endpoints, typically substations or switchyards, touch 230 kV+ lines inside the county [4]. Retail electric utilities with mapped service territory covering part of the county include Virginia Electric & Power and Northern Virginia Electric Cooperative, though these boundaries are approximate [5].
Loudoun County has a 12-month pause on new data center applications that is currently in force [6]. At the state level, Dominion Energy Virginia has a GS-5 large-load rate class effective January 1, 2027, which includes 14-year service commitments and minimum charges [7]. Virginia enacted a data center electricity consumption tax in the 2026-28 budget [8]. State laws HB153 and SB94 require localities to obtain a sound-profile site assessment for new high energy use facilities of 100 MW or more near homes or schools within 500 feet [9][11]. HB496 requires registered water users providing offsite water to report volumes supplied to data centers with DEQ air permits [10]. HB503, which is pending, would prevent utility costs related to serving data centers of 100 MW or more from being recovered from non-data-center customers unless rates substantially recover those costs from data centers [12].
Drafted by our local model from the numbered facts below, then checked sentence by sentence by a second model and a rules-based check.
Data center rules on record
Rule records come from The MW Desk legislation tracker, which includes rows from the Moratorium Nation dataset by Michael J. Bommarito (CC BY 4.0). Statuses change; confirm with the jurisdiction's own record.
Utilities on record
Virginia Electric & Power, Northern Virginia Electric Cooperative. (HIFLD/EIA-861 territory polygons; approximate and often overlapping.)
Market context on The MW Desk: Virginia: Northern Virginia + Richmond.
Sources
- [1] The archived HIFLD map shows about 141.4 miles of 230 kV-and-above transmission line inside Loudoun County, VA: 36.6 miles at 500 kV or more, 0.0 miles at 345 kV and 104.8 miles at 230 kV. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
- [2] The same map shows about 15.7 miles of 115–161 kV line in the county. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
- [3] Owners of record with the most mapped 115 kV+ line miles in the county: Virginia Electric & Power, The Potomac Edison. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
- [4] 12 named line endpoints touching 230 kV+ lines (usually substations or switchyards) are mapped inside the county. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
- [5] Retail electric utilities whose mapped service territory covers part of the county include: Virginia Electric & Power, Northern Virginia Electric Cooperative. Territory boundaries are approximate. Source: HIFLD Electric Retail Service Territories (EIA-861 based; archived by SeerAI, CC BY 4.0)
- [6] Loudoun County (county): 12-month pause on new data center applications. Status: in force, dated 2026-09-16. Source: DCD: Virginia's Loudoun County board votes to pause new data center applications
- [7] Virginia state/utility level, Dominion Energy Virginia: GS-5 large-load rate class (A separate class effective Jan 1, 2027, with 14-year service commitments and minimum charges). Status: enacted, dated 2027-01-01. Source: Dominion Energy: GS-5 Large Load Rate Class report
- [8] Virginia state/utility level, Virginia: 2026-28 budget, HB30 Item 3-5.24: data center electricity consumption tax. Status: enacted, dated 2026-06-29. Source: Virginia budget HB30 (reenrolled) Item 3-5.24: Data center electricity consumption tax
- [9] Virginia state/utility level, Virginia: HB153 (2026) (Adds Va. Code section 15.2-2209.4. Requires localities to obtain a sound-profile site assessment for new high energy use facilities of 100 MW or more near homes or schools within 500 feet; allows optional review of water, agriculture, parks, historic sites, and forestland). Status: enacted, dated 2026-04-13. Source: LIS Legislation Event History API - HB153 (2026, LegislationID 98797)
- [10] Virginia state/utility level, Virginia: HB496 (2026) (Requires registered water users that provide offsite water to report potable and reclaimed water volumes supplied to data centers with DEQ air permits, along with other use categories where available). Status: enacted, dated 2026-04-13. Source: LIS Legislation Event History API - HB496 (2026, LegislationID 99301)
- [11] Virginia state/utility level, Virginia: SB94 (2026) (Companion / identical enacted high energy use facility site-assessment bill; incorporated SB130). Status: enacted, dated 2026-04-13. Source: LIS Legislation Event History API - SB94 (2026, LegislationID 98848)
- [12] Virginia state/utility level, Virginia: HB503 (2026) (Would prevent utility costs substantially related to serving data center customers of 100 MW or more from being recovered from non-data-center customers unless rates substantially recover those costs from data centers). Status: pending, dated 2026-02-12. Source: LIS Legislation Event History API - HB503 (2026, LegislationID 99308)