County snapshot · records read 2026-11-09

Data center siting snapshot: Newton County, Georgia

What public records show about building a data center in Newton County: local and state data center rules, mapped high-voltage lines and the utilities on record. Every line links its source.

Mapped 230 kV+ line in county
31.6 mi
500 kV+: 4.6 · 345 kV: 0.0 · 230 kV: 27.0 mi
Named 230 kV+ line endpoints
n/a
Substation data not available in this dataset
Local data center rule records
1
State/utility records: 11

Line miles are measured from the archived HIFLD Transmission Lines layer inside the Census county boundary. Mapped lines are not available capacity.

What the public record shows

The archived HIFLD map indicates approximately 31.6 miles of 230 kV-and-above transmission line within Newton County, including 4.6 miles at 500 kV or more and 27.0 miles at 230 kV [1]. An additional 79.6 miles of 115–161 kV line are mapped in the area [2]. Georgia Power is the owner of record with the most mapped 115 kV+ line miles [3]. The dataset lacks a substation layer and does not map named line endpoints touching 230 kV+ lines, so substation presence cannot be confirmed from this record [4]. Retail electric utilities with mapped service territory covering part of the county include Georgia Power, Snapping Shoals Electric Membership Corporation, and the City of Covington [5].

A data center application moratorium is currently in force in Newton County, dated 2026-10-06 with a listed end date of 2026-12-16 [6]. At the state level, Georgia Power has certification for about 10 GW of new generation, enacted on 2026-09-01 [7]. A proposed temporary statewide pause was pledged by the Governor-elect on 2026-11-04 [8]. Several legislative attempts to regulate data center costs or impose moratoriums failed, including SB 410, SB 34, HB 1063, and HB 1059 [9][10][11][12].

Drafted by our local model from the numbered facts below, then checked sentence by sentence by a second model and a rules-based check.

Data center rules on record

JurisdictionRecordStatusDateSource
Newton CountyData center application moratorium (Resolution R-040726b, extended by Resolution R-100626A)in force through 2026-12-162026-10-06Newton County BOC agenda, Oct 6, 2026 (zoning item 2: Resolution R-100626A to extend the data center moratorium); Citizen Portal, Oct 7, 2026: board unanimously extends data center moratorium to Dec. 16
GeorgiaGovernor-elect pledge: temporary statewide pauseproposed2026-11-04DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections; The Guardian: Datacenters were on the ballot. US voters rejected them
Georgia PSC / Georgia PowerCertification of about 10 GW of new generationenacted2026-09-01Georgia PSC: Data Center Fact Sheet (Sep 2026)
GeorgiaSB 410 (2026)failed2026-03-10SB 410 (2025-2026) - Georgia General Assembly bill status
GeorgiaSB 34 (2025-2026)failed2026-02-25SB 34 (2025-2026) - Georgia General Assembly bill status
GeorgiaHB 1063 (2026)failed2026-02-18HB 1063 (2025-2026) - Georgia General Assembly bill status
GeorgiaHB 1059 (2026)failed2026-02-02HB 1059 (2025-2026) - Georgia General Assembly bill status, 'Data Center Impact Assessment and Development Moratorium Act of 2026'
GeorgiaHB 1012 (2026)failed2026-01-28HB 1012 (2025-2026) - Georgia General Assembly bill status
GeorgiaSB 421 (2026)failed2026-01-27SB 421 (2025-2026) - Georgia General Assembly bill status, 'Data Center Transparency Act'
GeorgiaSB 408 (2026)failed2026-01-16SB 408 (2025-2026) - Georgia General Assembly bill status
GeorgiaHB 559 (2025)failed2025-02-21HB 559 (2025-2026) - Georgia General Assembly bill status
GeorgiaHB 1192 (2024)vetoed2024-05-07HB 1192 (2023-2024) - Georgia General Assembly bill status

Rule records come from The MW Desk legislation tracker, which includes rows from the Moratorium Nation dataset by Michael J. Bommarito (CC BY 4.0). Statuses change; confirm with the jurisdiction's own record.

Utilities on record

Georgia Power, Snapping Shoals Electric Membership Corporation, City of Covington (GA). (HIFLD/EIA-861 territory polygons; approximate and often overlapping.)

Market context on The MW Desk: Atlanta + Georgia secondary.

Have a parcel here? A Quick Screen checks the nearest mapped lines and substations, FEMA flood zone, these rules and the utility for one parcel, with a red-flag list and the questions to ask the utility. $149, delivered in 24 hours.

Sources

  1. [1] The archived HIFLD map shows about 31.6 miles of 230 kV-and-above transmission line inside Newton County, GA: 4.6 miles at 500 kV or more, 0.0 miles at 345 kV and 27.0 miles at 230 kV. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
  2. [2] The same map shows about 79.6 miles of 115–161 kV line in the county. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
  3. [3] Owners of record with the most mapped 115 kV+ line miles in the county: Georgia Power. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
  4. [4] Substation data not available in this dataset for this county: the dataset has no substation layer, and no named line endpoints touching 230 kV+ lines (the proxy used for substations) are mapped inside the county. This does not mean there are no substations. Source: HIFLD Transmission Lines (archived by SeerAI, CC BY 4.0)
  5. [5] Retail electric utilities whose mapped service territory covers part of the county include: Georgia Power, Snapping Shoals Electric Membership Corporation, City of Covington (GA). Territory boundaries are approximate. Source: HIFLD Electric Retail Service Territories (EIA-861 based; archived by SeerAI, CC BY 4.0)
  6. [6] Newton County (county): Data center application moratorium (Resolution R-040726b, extended by Resolution R-100626A). Status: in force, dated 2026-10-06, listed end date 2026-12-16 (checked 2026-11-09). Source: Newton County BOC agenda, Oct 6, 2026 (zoning item 2: Resolution R-100626A to extend the data center moratorium)
  7. [7] Georgia state/utility level, Georgia PSC / Georgia Power: Certification of about 10 GW of new generation. Status: enacted, dated 2026-09-01. Source: Georgia PSC: Data Center Fact Sheet (Sep 2026)
  8. [8] Georgia state/utility level, Georgia: Governor-elect pledge: temporary statewide pause. Status: proposed, dated 2026-11-04. Source: DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections
  9. [9] Georgia state/utility level, Georgia: SB 410 (2026) (Would repeal the data center equipment sales/use tax exemption while preserving prior certificates). Status: failed, dated 2026-03-10. Source: SB 410 (2025-2026) - Georgia General Assembly bill status
  10. [10] Georgia state/utility level, Georgia: SB 34 (2025-2026) (Would prohibit utility costs caused by commercial data centers from being included in rates unless recovered solely or substantially from data centers). Status: failed, dated 2026-02-25. Source: SB 34 (2025-2026) - Georgia General Assembly bill status
  11. [11] Georgia state/utility level, Georgia: HB 1063 (2026) (Would require electric utilities to protect residential and retail customers from costs associated with data center construction and operation). Status: failed, dated 2026-02-18. Source: HB 1063 (2025-2026) - Georgia General Assembly bill status
  12. [12] Georgia state/utility level, Georgia: HB 1059 (2026) ("Data Center Impact Assessment and Development Moratorium Act of 2026"; would impose a statewide development moratorium and create an assessment commission). Status: failed, dated 2026-02-02. Source: HB 1059 (2025-2026) - Georgia General Assembly bill status, 'Data Center Impact Assessment and Development Moratorium Act of 2026'